Rita Dominic Unveils lover’s identity in Christmas photos
A Nollywood actress, Rita Dominic, has left friends and fans talking on social media after she shared rare loved-up photos of herself with her lover. The 45-year-old film star shared […]
Welcome to Online Radio
The Leading Lifestyle Internet Radio
Music 24/7 - Africana
Online Radio
Music 24/7 - International
Online Radio
Music 24/7 - Gospel
Online Radio
Music 24/7 - Latin America
Online Radio
Talk Shows - Stay Updated
Online Radio
Pillars and Plants - Gospel
Online Radio
Audio Stories - A new movie experience
Online Radio
Oluwaseye Ogunsanya December 26, 2020 44
Due to the full closure of Third Mainland Bridge on the midnight of Christmas Day, the residents of Lagos might be faced with traffic difficulties amid the Christmas holiday.
The bridge will remain closed until midnight of December 28 as it is undergoing repairs.
Earlier, the Federal Government had announced that the bridge will be shut for 72 hours to cast concrete on the expansion joints.
While making the announcement, Federal Controller of Works in Lagos, Olukayode Popoola said the reason for the repairs is to prevent vibration of the bridge.
“There is going to be a total closure of Third Mainland Bridge in order to allow for the casting of three number expansion joints on the Island Bound lane. The effective date of the closure will be from 12:00 midnight of 25th of December. So people will be allowed to use the Third Mainland Bridge to celebrate Christmas.’’
“By the time the Christmas is winding down which is 12:00 midnight, we are going to close it, so that we will be able to cast the concrete on Saturday the 26th and on 27th we cast again. And we need about 72 hours for this concrete to set. Therefore, the opening will be on the 28th December midnight, that is 72-hour closure,” he said.
Popoola explained that the full closure of the bridge is necessary because, “If we allow vehicles to be moving on one lane, there is going to be vibrations and the concrete will not set properly.”
He also announced that there will be a partial closure of the Lagos-Ibadan Expressway for 48 hours, beginning from Monday, December 28 to Tuesday, December 29, for the completion of some repairs.
The Third Mainland Bridge in Lagos was partially shut on July 24 for rehabilitation works and a series of repairs.
The repair expected to last six months was extended by one month due to the #EndSARS protests in Lagos thereby extending the completion date from January 2021 to February.
The bridge is the longest of the three bridges connecting Lagos Island to the Mainland.
Tagged as: Lagos, Christmas, Third Mainland Bridge, Lagos-Ibadan Expressway.
Oluwaseye Ogunsanya December 26, 2020
A Nollywood actress, Rita Dominic, has left friends and fans talking on social media after she shared rare loved-up photos of herself with her lover. The 45-year-old film star shared […]
Post comments (0)